Springbank Dam Rehabilitation Project

The Springbank Dam Rehabilitation Project was initiated to ensure the safe operation of Springbank Dam. Studies in 2000 and 2002 recommended that the dam be rehabilitated to meet provincial dam safety requirements. Deficiencies were identified including:

  • Erosion protection damaged in the July 9, 2000 Thames River flood,
  • Failing stop logs prone to blockage by debris and operational challenges, and
  • Concrete deterioration.

An Environmental Assessment was undertaken to look at the alternatives (Environmental Assessment Report Springbank Dam (2003) and Appendices). The rehabilitation completed focused on replacing the failing stop logs with gates, leaving other work to be done in the future.

Top priorities for the Rehabilitation Project:

  • Improved Public Safety – Safety of people and property remain the priority of the UTRCA. The Springbank Dam structure is in poor condition and requires upgrading and repair to ensure that it does not compromise the UTRCA flood control system. Various public safety upgrades are also proposed as part of the project.
  • Environmental Health – The UTRCA promotes a healthy environment and wishes to ensure that the project proceeds in a manner that does not, in any way, degrade the health of the ecosystem.
  • Stakeholder Participation – The rehabilitation of Springbank Dam is an inclusive project. Various stakeholders have been involved in the project through the EA process and through stakeholder participation in the Science and Engineering Technical Committee initiated by the City of London.

Timeline

  • July 9, 2000: The dam is overtopped during a flood due to debris accumulation, damaging the south bank and raising concerns about the safety of the structure.
  • May 2, 2002: Dam Safety Assessment completed by Acres International (now Hatch-Acres). Report identified the need for better debris passage, improved operational efficiency, and repairs to the portions of the dam damaged in 2000.
  • 2002: City of London received funding to rehabilitate the dam and repair the failed erosion protection through the Ontario Sports, Culture and Tourism Program and the Canada-Ontario Infrastructure Program.
  • August 2003: Project description report and class environmental assessment report completed.
  • October 22, 2003: Environmental assessment open house/public meeting held at Byron Public Library, London.
  • January 2004: Environmental assessment completed; public and agency review period ended January 12, 2004.
  • August 3, 2004: UTRCA hosts stakeholder meeting regarding fish ladder issue at Byron Public Library.
  • October 29, 2004: Science and Engineering Technical Committee (SETC) initiated by the City of London, chaired by the Ministry of Natural Resources, to investigate issues raised about fish passage at the structure and potential for a fishway.
  • November 2004 and continuing: SETC information-sharing leads to discussion on fish passage at existing dam and for proposed gate rehabilitation project at dam. Field investigations by Committee members are initiated to inventory species and distribution.
  • September 2005: Fish Passage Monitoring Framework completed by Ministry of Natural Resources with input from SETC.
  • October 2005: The rehabilitation of Springbank Dam, which was set to begin on October 1, 2005, has been postponed due to developments including but not limited to: delay in the issuance of work permits; need to assemble more baseline data for fisheries assessment; dramatic increase in the project costs due to recent developments. The intention is to implement this project in 2006. Options for next year are being studied by the City of London and the engineering consultant. The City of London is reviewing the project budget, which may rise significantly due to postponement. The City is currently seeking additional funding from Provincial and Federal partners who were originally sharing the costs in 1/3 portions. The UTRCA is pleased that the City of London has gained an extension to the project’s timeline as it will allow more time to assess the fish movement at Springbank Dam.
  • April to June 2006: Fish Passage Baseline Studies undertaken by Biotactic. Study supported by City of London, Upper Thames River Conservation Authority, Ministry of Natural Resources, Fisheries and Oceans Canada.
  • June 2006: Tender release by the City of London.
  • August 2006: Updating of Agency approvals, Tender approval by the City of London.
  • September 2006: Construction started on the rehabilitation of Springbank Dam. A construction tender was awarded by the City of London in August 2006 to MacLean Taylor Construction Ltd. of St. Marys, Ontario. Hatch Acres of Niagara Falls are the Consulting Engineers overseeing the construction.
  • Fall 2006: Construction progress slowed by high water levels. The Thames River average flow at Byron over the month of October 2006 was the highest ever recorded in October (since records began in 1922). The November 2006 average flow was the fifth highest November on record, and December 2006 average flow was the second highest December on record.
  • February 2007: City of London issued a press release indicating that, due to weather-related delays, construction will not be complete in time to allow filling of the Springbank Reservoir for the normal 2007 summer season.
  • April, May and June 2007: As required by MNR, all construction activities in river ceased to allow for spring fish migration.
  • July 2007: Construction at Springbank resumes. Project scheduled to be completed in fall ’07.
  • June 2008: One of the gate hinges fails during commissioning, rendering the dam inoperable.
  • January 2018: London City Council votes to decommission the Springbank Dam.